Client | Bangladesh Power Development Board (BPDB) |
Status | Ongoing |
Location | Palash, Narsingdi, Ghorasal |
Project Excecution Period | 960 days |
Name of Owner’s Engineer (OE) | JV of TUV SUD South Asia Pvt Limited,
India and Power-Energy Management & Engineering Company, Bangladesh. |
Contract Effective Date (OE) | 08.03.2017 |
Name of the EPC Contractor | Consortium of Alstom( Switzerland) and China Machinery Imp. & Exp. Corporation, China. |
Contract Effective Date (EPC) | 22.01.2017 |
Project Cost ( EPC ) | USD. 140.437 Million |
Contract Value | USD. 1.34 Million |
Technical Data | |
|
Symple Cycle (GT) : 260.30MW Combined Cycle : 416.30MW |
|
Gas Turbine, Generator ,Transformer, HRSG, Cooling Tower etc. |
|
53.37% |
|
Natural Gas |
Description of provided services : | |
-Checking/witnessing the 72 hours continuous trial and commercial operation of the power plant including sub-stations. -Checking/witnessing the performance tests to be carried out by the contractor during the period of 90 days subsequent to initial commercial operation commenced with the successful completion of 72 hours continuous operation test (COT). -Assisting BPDB in providing the contractor with Provisional Acceptance Certificate (PAC) and Final Acceptance Certificate (FAT) . -Checking and placed for approval by the engineer of the project of all electrical, mechanical, civil and I&C “As Built” drawings submitted by the turnkey contractor. -Checking various (technical, progress and test reports etc.) and similar documents to be prepared and submitted by the turnkey contractor during execution of the erection work and keeping BPDB informed of the actual progress of work. -Studying and submitting comments on operation and maintenance manuals of plant equipment submitted by turnkey contractor and correcting the manuals as necessary. -Establishing in consultant with BPDB a procedure for checking and approval of invoice for payment of the turnkey contractor and certifying the same for further necessary action by concerned project officials. -Arranging periodical coordination meetings with BPDB and contractor and submitting the reports of the same to BPDB and contractor. -Checking the month/quarterly progress report submitted by the turnkey contractor and preparing comments on them. -Assisting all concerned agencies to ensure proper and timely completion of the electrical, mechanical, civil items of works as well as smooth commissioning of the plant. |